Indiacon Civil

Subjects › Cost Management › Intermediate

Life-cycle cost

Intermediate Cost Management Reviewed 24 Oct 2026 2 min read

The cheapest option to build is not always the cheapest to own. Life-cycle cost adds up all the costs of an asset over its life: initial construction, operation, energy, maintenance, repair, replacement of parts and, at the end, disposal, less any salvage value. Comparing options on this basis avoids choices that save money today and cost much more later.

Because money now is worth more than money later, future costs are converted to present value with a discount rate. A cost C in year n has present value C / (1 + i)^n. A uniform annual cost A over n years has present value A × [1 − (1 + i)^−n] / i, the uniform-series present worth factor. The option with the lower total present value is cheaper over its life.

Diagram: Indiacon original, not to scale.

Typical applications include choosing between flexible and rigid pavements, between pipe materials, between plain and corrosion-protected reinforcement in harsh exposure, and between building services with different energy use. The answer can depend strongly on the discount rate and the analysis period, so sensitivity tests are part of any honest study.

Life-cycle costing works best with good data on maintenance and service life, which asset management systems build over time. It is also the basis for whole-life value in public procurement.

Tip

Show the result for a range of discount rates; decision makers trust a robust answer.

Key formulas
  • Present value of a future cost: PV = C / (1 + i)^n
  • Present value of a uniform annual cost: PV = A × [1 − (1 + i)^−n] / i
Common mistake

Comparing options on build cost alone.

Solved example

Problem. Option A costs Rs 10 lakh to build and Rs 0.5 lakh a year to maintain. Option B costs Rs 12 lakh and Rs 0.345 lakh a year. Compare them over 30 years at 6 percent.

  1. Annuity factor = [1 − 1.06^−30] / 0.06 = 13.7648.
  2. A: 10 + 0.5 × 13.7648 = 16.88 lakh.
  3. B: 12 + 0.345 × 13.7648 = 16.75 lakh.
  4. B is slightly cheaper over its life despite costing more to build; the margin is small, so test other discount rates.

Answer. A ≈ Rs 16.88 lakh; B ≈ Rs 16.75 lakh; B marginally cheaper

Quick quiz

1What costs are included in life-cycle cost?

Construction, operation, maintenance, replacement and disposal, less salvage.

2Why discount future costs?

Money now is worth more than the same amount later.

3Why run sensitivity tests?

The result can change with the discount rate and analysis period.

Code note
  • AACE International Recommended Practices (USA): Cost engineering practices, including estimate classification.

Cited by number and clause only. We do not reproduce clause text, tables or figures (BIS Act 2016, s.10(5) and s.11). Check the current edition and amendments before use.

References and further reading

Standard texts, listed in no order of merit. We do not copy text, figures, tables or solved problems from any book; our explanations and examples are original.

  • Q. W. Fleming, J. M. Koppelman, Earned Value Project Management, Project Management Institute, latest edition.
  • K. K. Chitkara, Construction Project Management, McGraw Hill Education (India), latest edition.

Free and official sources

All references for this subject →