Budgets
A project budget is the approved amount for delivering the scope, broken down so that each part of the work has its own allowance and someone responsible for it. It is built from the cost estimate but is more than a number: it is a control tool, phased over time and tied to the work breakdown structure.
Budgets mature with the design. A concept estimate, from cost per square metre or per kilometre of similar projects, may be accurate only to plus or minus 30 percent or more. A detailed estimate from measured quantities and rate analysis narrows that to around plus or minus 10 percent. Each stage should state its accuracy range and its assumptions. The approved budget at award, the cost baseline, includes the contract sum, owner's costs such as land, design, supervision and utility shifting, taxes, and contingency reserves for known risks. A management reserve for unknown risks is held separately and released only by approval.
Phasing the budget month by month, using the schedule, gives the planned value curve, the S-curve against which progress and cash needs are measured. Budget transfers between items, change orders and use of contingency are recorded formally so the current budget always reconciles to the original. Public works budgets also follow financial rules for sanction, technical approval and re-appropriation.
State the accuracy range and the date of prices on every estimate that feeds a budget.
Budget at completion (BAC) = Σ control account budgetsCost baseline = BAC + contingency reserveTotal project budget = cost baseline + management reservePhased budget → planned value S-curve
Spending contingency on scope additions without a formal change record, so the budget no longer reconciles.
Problem. A road project has a detailed estimate of ₹240 crore. Contingency reserve for identified risks is 6 percent, and management reserve 3 percent of the estimate. Find the cost baseline and total budget.
- Contingency = 0.06 × 240 = ₹14.4 crore; cost baseline = ₹254.4 crore.
- Management reserve = 0.03 × 240 = ₹7.2 crore.
- Total budget = 254.4 + 7.2 = ₹261.6 crore.
- Report to management against the baseline; draw on reserves only with approval.
Answer. Cost baseline ₹254.4 crore; total budget ₹261.6 crore
Quick quiz
1What is a cost baseline?
The approved, time-phased budget including contingency, used to measure performance.
2Difference between contingency and management reserve?
Contingency covers identified risks; management reserve covers unknown risks and needs approval.
3Why phase the budget?
To get the planned value curve for monitoring progress and cash flow.
- IS 15883 (series) (India): Guidelines for construction project management, one part per knowledge area.
- AACE International Recommended Practices (USA): Cost engineering practices, including estimate classification.
Clauses and documents to read
- IS 15883 (Part 3):2015 (cost management)
- AACE International Recommended Practice 18R-97 (cost estimate classification, cited by number)
Cited by number and clause only. We do not reproduce clause text, tables or figures (BIS Act 2016, s.10(5) and s.11). Check the current edition and amendments before use.
References and further reading
Standard texts, listed in no order of merit. We do not copy text, figures, tables or solved problems from any book; our explanations and examples are original.
- Q. W. Fleming, J. M. Koppelman, Earned Value Project Management, Project Management Institute, latest edition.
- K. K. Chitkara, Construction Project Management, McGraw Hill Education (India), latest edition.
Free and official sources
Found an error? Write to indiacongroupofengineers [at] gmail [dot] com. For corrections and feedback. We never ask for payment or personal details.