Direct and indirect costs
Construction cost is split into direct and indirect costs because they behave differently and are controlled differently. Direct costs are those that can be traced to a specific item of permanent work: the cement, steel, aggregate and labour in a column, the hire of the excavator digging a trench, the subcontract for waterproofing. They are estimated from quantities multiplied by unit rates.
Indirect costs support the work as a whole but cannot be tied to one item. Site overheads, sometimes called preliminaries or general conditions, include site staff and supervision, temporary offices, stores, fencing and security, site power and water, safety measures, testing laboratories, insurance, bank guarantees and permits. Many of these are time-related: they accrue every day the site is open, so delays raise them directly. Others are fixed, like mobilisation, or value-related, like insurance premiums. Head office overheads cover the contractor's corporate costs and are recovered as a percentage. Profit is added on top, along with a contingency for risk.
The distinction matters in tendering, where indirect costs may be priced as separate items or spread into unit rates; in time-cost trade-off analysis, where shortening the project reduces time-related indirects; and in claims for delay, where prolongation costs are mainly indirect. Good cost reporting keeps the two separate so that management can see whether overruns come from productivity on the work itself or from the project taking longer.
Direct cost = Σ quantity × unit rateTime-related indirect = daily rate × durationTotal = direct + indirect + head office overhead + profit + contingencyOverhead percent = indirect / direct × 100
Problem. A building job has direct cost ₹18.0 crore. Site overheads are ₹4.5 lakh per month over 20 months plus ₹30 lakh fixed. Head office overhead 5 percent and profit 7 percent apply on total cost. Find the bid price.
- Time-related overheads = 4.5 × 20 = ₹90 lakh; plus fixed ₹30 lakh, so indirect = ₹1.2 crore.
- Cost = 18.0 + 1.2 = ₹19.2 crore.
- Add 5 percent head office: ₹20.16 crore; add 7 percent profit: ₹21.57 crore.
- If the job runs 4 months late, time-related costs rise by ₹18 lakh.
Answer. About ₹21.6 crore; each month of delay adds ₹4.5 lakh
Quick quiz
1Give two examples of direct cost.
Materials and labour for a specific item (also plant for that item, subcontracts).
2Why do delays raise indirect cost?
Many indirect costs are time-related.
3What are preliminaries?
Site overheads and general conditions supporting the whole work.
- IS 15883 (series) (India): Guidelines for construction project management, one part per knowledge area.
Clauses and documents to read
- IS 15883 (Part 3):2015 (cost management)
Cited by number and clause only. We do not reproduce clause text, tables or figures (BIS Act 2016, s.10(5) and s.11). Check the current edition and amendments before use.
References and further reading
Standard texts, listed in no order of merit. We do not copy text, figures, tables or solved problems from any book; our explanations and examples are original.
- Q. W. Fleming, J. M. Koppelman, Earned Value Project Management, Project Management Institute, latest edition.
- K. K. Chitkara, Construction Project Management, McGraw Hill Education (India), latest edition.