A foundation is shallow when it transfers load to soil close to the surface, typically at a depth not much more than its width. Pad, strip, combined footings and rafts are shallow foundations. A foundation is deep when it carries load down through weak or compressible layers to firmer strata, or spreads it along its length by side friction. Piles, piers, caissons and well foundations are deep foundations.

The choice is driven by soil, load and cost. If competent soil lies near the surface and loads are moderate, shallow foundations are cheaper and faster. Deep foundations become necessary when the top soil is soft, loose, expansive, liable to scour or liquefaction, or when loads are heavy, as for towers, bridges and industrial plant. They are also used where uplift or lateral loads must be resisted, for example for transmission towers, wharves and wind turbines, and where a future excavation next door could undermine a shallow footing.

Diagram: Indiacon original, not to scale.

A raft sits between the two: it spreads load over the whole plan area and can float a building on soft ground by removing soil whose weight equals much of the building's load (a compensated foundation). A piled raft combines both, using piles to reduce settlement while the raft still carries part of the load. In bridges over rivers, well foundations are used where scour is deep. Every choice should start with a proper site investigation, because the wrong foundation type is far costlier to fix than any other design error.

Key formulas
  • Shallow: Df ≤ B approximately (Terzaghi's definition)
  • Gross pressure: q = (P + W_f + W_s) / A
  • Compensated raft: net pressure = q − γ Df
  • Pile capacity: Q = Q_base + Q_shaft
Solved example

Problem. A building applies 60 kPa average pressure. Soft clay allows a net pressure of only 30 kPa. With soil γ = 18 kN/m³, how deep must a raft be placed to act as a fully compensated foundation?

  1. Full compensation means the weight of excavated soil equals the building pressure.
  2. γ Df = 60 kPa, so Df = 60 / 18 = 3.3 m.
  3. For a partly compensated raft allowing 30 kPa net, γ Df = 30, so Df = 1.7 m.
  4. Heave of the excavation base and groundwater must be checked.

Answer. About 3.3 m for full compensation (1.7 m for partial)

Quick quiz

1When is a foundation called shallow?

When its depth is roughly no more than its width.

2Name two reasons to choose piles.

Soft or loose top soils; heavy loads; uplift, lateral loads, scour or liquefaction.

3What is a compensated raft?

One placed deep enough that the weight of excavated soil offsets much of the building load.

Code note
  • IS 1904 (India): Design and construction of foundations in soils: general requirements.
  • IS 2911 (series) (India): Design and construction of pile foundations.
  • IS 2950 (Part 1) (India): Design and construction of raft foundations.

Clauses and documents to read

  • IS 1904:1986 (design and construction of foundations in soils)
  • IS 2950 (Part 1):1981 (raft foundations)
  • IS 2911 (Part 1/Sec 2):2010 (bored cast in-situ piles)

Cited by number and clause only. We do not reproduce clause text, tables or figures (BIS Act 2016, s.10(5) and s.11). Check the current edition and amendments before use.

References and further reading

Standard texts, listed in no order of merit. We do not copy text, figures, tables or solved problems from any book; our explanations and examples are original.

  • B. M. Das, Principles of Foundation Engineering, Cengage, latest edition.
  • J. E. Bowles, Foundation Analysis and Design, McGraw Hill, 5th edition.
  • M. J. Tomlinson, Pile Design and Construction Practice, CRC Press, latest edition.