Stress checks at transfer and service
A prestressed member must be checked at two critical stages. At transfer, the prestress is at its highest, because losses have not yet occurred, while the only load acting is usually the member's self-weight. At service, the prestress has fallen to its effective value after losses, while the full dead and imposed loads act. A section that is fine at one stage can fail the other.
At each stage the top and bottom fibre stresses come from three parts: the uniform compression P over A, the bending from the eccentric prestress, P times e over Z, and the bending from the external moment, M over Z. With the tendon below the centroid, prestress bending compresses the bottom and tensions the top; gravity moment does the opposite. Each fibre at each stage is compared with the permissible compressive and tensile stresses for that stage, which gives four inequalities in all.
At transfer the risk is too much tension at the top near the supports, where self-weight moment is small, and too much compression at the bottom. Concrete at transfer is also younger and weaker, so permissible values are lower. At service the risk is tension at the bottom at mid-span under full load. The ratio of effective to initial prestress, often written as eta, links the two stages.
Plotting these inequalities, the Magnel diagram, shows the feasible range of prestress and eccentricity at once. Debonding or deflecting some strands near the ends of pre-tensioned members reduces the transfer tension at the top where self-weight cannot counter it.
Check the transfer stage at the support region too, where self-weight moment is near zero.
Top fibre: σ_t = P / A − P e / Z_t + M / Z_tBottom fibre: σ_b = P / A + P e / Z_b − M / Z_b (compression positive)Service force P_e = η P_i
Using the same permissible stresses at transfer and at service, although the concrete is younger at transfer.
Problem. A 300 × 800 mm beam spans 15 m. At transfer P_i = 1 800 kN at e = 250 mm; self-weight is 6 kN/m. At service η = 0.85 and an extra moment of 300 kNm acts. Find top and bottom stresses at mid-span at both stages (compression positive).
- A = 240 000 mm², Z = 300 × 800² / 6 = 3.2 × 10⁷ mm³. Self-weight moment M_g = 6 × 15² / 8 = 168.75 kNm.
- Transfer: P/A = 7.50, P e / Z = 1 800 000 × 250 / 3.2 × 10⁷ = 14.06, M_g / Z = 5.27 MPa. Top = 7.50 − 14.06 + 5.27 = −1.29 MPa (tension); bottom = 7.50 + 14.06 − 5.27 = 16.29 MPa.
- Service: P_e = 0.85 × 1 800 = 1 530 kN; P/A = 6.38, P e / Z = 11.95, M / Z = 468.75 × 10⁶ / 3.2 × 10⁷ = 14.65 MPa.
- Top = 6.38 − 11.95 + 14.65 = 9.07 MPa; bottom = 6.38 + 11.95 − 14.65 = 3.68 MPa (both compression).
Answer. Transfer: top −1.29 MPa, bottom 16.29 MPa. Service: top 9.07 MPa, bottom 3.68 MPa
Quick quiz
1When is prestress highest?
At transfer, before time-dependent losses.
2Where is tension most likely at transfer?
At the top fibre, especially near the supports.
3What is the Magnel diagram?
A plot of the four stress inequalities showing feasible prestress and eccentricity.
- IS 1343 (India): Design and construction of prestressed concrete.
- IRC:112 (India): Code of practice for concrete road bridges.
- EN 1992 (Eurocode 2) (Europe): Design of concrete structures.
Cited by number and clause only. We do not reproduce clause text, tables or figures (BIS Act 2016, s.10(5) and s.11). Check the current edition and amendments before use.
References and further reading
Standard texts, listed in no order of merit. We do not copy text, figures, tables or solved problems from any book; our explanations and examples are original.
- N. Krishna Raju, Prestressed Concrete, McGraw Hill Education (India), latest edition.
- T. Y. Lin, N. H. Burns, Design of Prestressed Concrete Structures, Wiley, 3rd edition.