Units of measurement
Every quantity in an estimate or bill must be measured in a clear, agreed unit, or the contractor and client will argue about what was meant and how much was done. Standard methods of measurement fix the unit, the rules for what is included and deducted, and the precision for each type of work, so that bills from different estimators can be compared and paid fairly.
Typical units follow the nature of the work. Earthwork in excavation and filling is measured in cubic metres. Concrete and masonry are also in cubic metres, while thin items such as plaster, flooring, painting and formwork are in square metres. Linear items such as skirting, pipes, kerbs, railings and fencing are in running metres. Reinforcement and structural steel are by weight in kilograms or tonnes. Doors, windows, fixtures, manholes and fittings are counted in numbers. Lump sums are used only where measurement is impractical.
Measurement rules state, for example, whether openings in walls are deducted (small ones usually are not), how laps in reinforcement are treated, whether work in foundations is measured separately from superstructure, and whether working space or slopes in excavation are included. Dimensions are taken to a stated precision, usually to the nearest centimetre for linear dimensions and to two decimal places for areas and volumes. In India IS 1200 sets these rules part by part for each trade; public works departments add their own schedule descriptions and item units.
Volume (m³) = L × B × DArea (m²) = L × B (or L × H)Weight of bar (kg) = length × d² / 162Quantity to stated precision; round only at the end
Problem. A 230 mm brick wall is 12.4 m long and 3.0 m high with one door 1.0 × 2.1 m and two windows 1.2 × 1.2 m. Find brickwork volume and plaster area on one face.
- Gross volume = 12.4 × 3.0 × 0.23 = 8.556 m³.
- Openings: door 2.10 m², windows 2 × 1.44 = 2.88 m²; total 4.98 m² × 0.23 = 1.145 m³.
- Net brickwork = 7.41 m³.
- Plaster one face = 37.2 − 4.98 = 32.22 m² (plus jambs as per the measurement rules).
Answer. Brickwork ≈ 7.41 m³; plaster ≈ 32.2 m² one face
Quick quiz
1In what unit is reinforcement measured?
By weight, in kilograms or tonnes.
2Why are standard measurement rules needed?
So quantities are measured and paid consistently.
3Which Indian standard covers methods of measurement?
IS 1200 (various parts).
- IS 1200 (series) (India): Method of measurement of building and civil engineering works, one part per trade.
Clauses and documents to read
- IS 1200 (Part 1):1992 (earthwork)
- IS 1200 (Part 2):1974 (concrete work)
- IS 1200 (Part 3):1976 (brickwork)
- IS 1200 (Part 12):1976 (plastering and pointing)
Cited by number and clause only. We do not reproduce clause text, tables or figures (BIS Act 2016, s.10(5) and s.11). Check the current edition and amendments before use.
References and further reading
Standard texts, listed in no order of merit. We do not copy text, figures, tables or solved problems from any book; our explanations and examples are original.
- B. N. Dutta, Estimating and Costing in Civil Engineering, UBS Publishers, latest edition.
Free and official sources
Found an error? Write to indiacongroupofengineers [at] gmail [dot] com. For corrections and feedback. We never ask for payment or personal details.