Specifications
Drawings show what is to be built and where; specifications describe the quality of materials and workmanship and how it will be checked. Together with the bill of quantities and conditions of contract, they define the contract. A vague specification leads to disputes and poor work; a clear one lets every bidder price the same thing and lets the engineer accept or reject work objectively.
Specifications may be general, applying to standard items across many works, such as a public works department's standard specifications, or particular, written for a specific project's special requirements. They may be prescriptive, stating materials, proportions and methods, or performance-based, stating required properties and test results while leaving the method to the contractor. Most combine both: concrete may be specified by grade, maximum water-cement ratio and minimum cement content (performance plus limits), while curing is prescribed.
A good specification clause covers materials (standards they must meet), workmanship (method, tolerances, sequence), testing and acceptance (tests, frequency, criteria, and what happens on failure), and measurement and payment. It refers to standards by number and edition rather than repeating their text, avoids conflict with drawings and other clauses, and uses clear language: 'shall' for requirements. An order of precedence in the contract decides which document governs if they conflict.
Where a specification and a drawing disagree, site staff should not choose the easier option; they should raise a query and record the engineer's decision.
Read the specification and drawings together at tender stage and raise conflicts as queries before pricing.
Clause structure: scope → materials → workmanship → testing → acceptance → measurementAcceptance by test: result ≥ specified value at stated frequencyOrder of precedence resolves conflicts
Copying an old specification without checking that the standards it cites are still current.
Problem. A specification requires one cube set per 30 m³ of concrete placed per day, with a minimum of one set per day. A pour of 95 m³ is made in one day. How many sets are needed?
- 95 / 30 = 3.17, so at least 4 sets are needed.
- The daily minimum of 1 set is exceeded, so 4 sets govern.
- Each set usually has 3 cubes per test age, so prepare cubes for each test age required.
Answer. At least 4 sets of cubes
Quick quiz
1What do specifications describe?
Quality of materials and workmanship, and how it is tested and accepted.
2What is a performance specification?
One that states required results rather than methods.
3Why refer to standards by number?
To avoid repeating text and to keep the reference exact.
- IS 456 (India): Plain and reinforced concrete: general rules for materials, durability, design and construction.
- IS 1200 (series) (India): Method of measurement of building and civil engineering works, one part per trade.
Clauses and documents to read
- IS 456:2000 cl. 15 (sampling and strength tests)
- IS 456:2000 cl. 16 (acceptance criteria)
- CPWD Specifications (cited by name; use the current edition)
- MoRTH Specifications for Road and Bridge Works (cited by name)
Cited by number and clause only. We do not reproduce clause text, tables or figures (BIS Act 2016, s.10(5) and s.11). Check the current edition and amendments before use.
References and further reading
Standard texts, listed in no order of merit. We do not copy text, figures, tables or solved problems from any book; our explanations and examples are original.
- B. N. Dutta, Estimating and Costing in Civil Engineering, UBS Publishers, latest edition.
Free and official sources
Found an error? Write to indiacongroupofengineers [at] gmail [dot] com. For corrections and feedback. We never ask for payment or personal details.