Rate analysis
Rate analysis works out the cost of one unit of an item of work, such as one cubic metre of M25 concrete or one square metre of 12 mm plaster, by building it up from its ingredients: materials, labour, plant, overheads and profit. It is the link between quantities and money, and the basis of schedules of rates, tender pricing and the evaluation of extra items.
For each item, the analysis lists the quantity of each material per unit, including wastage, at current delivered prices; the labour by category (mason, helper, bar bender) in man-days per unit, from output norms or site records, at current wages; and the hire or owning and operating cost of plant per unit, from its output per hour. Sundries cover small tools, water and minor consumables. Contractor's overheads and profit, usually a combined percentage, are added. Taxes are treated as the contract requires.
Accuracy depends on realistic outputs and prices. Published schedules of rates and their analyses of rates from public works departments provide norms, but site conditions, method, lead and lift of materials, and scale change actual costs. A rate analysis should state its date, location and assumptions, so it can be updated when prices change. Comparing analysed rates with market quotations and past tenders keeps estimates honest.
Check the lead (distance) and lift (height) of materials for the actual site; they can shift rates noticeably.
Unit rate = (materials + labour + plant + sundries) × (1 + overhead and profit)Material per m³ including wastage = theoretical × (1 + wastage)Labour cost = Σ man-days per unit × wage ratePlant cost per unit = hourly cost / output per hour
Problem. Analyse 1 m³ of M20 concrete with 320 kg cement at ₹7/kg, 0.45 m³ sand at ₹1 800/m³, 0.85 m³ aggregate at ₹1 600/m³, labour ₹950, mixer and vibrator ₹300, sundries ₹100, and 15 percent overhead and profit.
- Cement = ₹2 240; sand = ₹810; aggregate = ₹1 360. Materials = ₹4 410.
- Add labour ₹950, plant ₹300, sundries ₹100: subtotal ₹5 760.
- Overhead and profit 15 percent = ₹864.
- Rate = ₹6 624 per m³ (excluding taxes and formwork and reinforcement).
Answer. About ₹6 620 per m³
Quick quiz
1What are the main components of a rate analysis?
Materials, labour, plant, sundries, overheads and profit.
2Why include wastage?
Some material is always lost in handling and placing.
3Why date a rate analysis?
Prices and wages change, so the rate must be updatable.
- IS 1200 (series) (India): Method of measurement of building and civil engineering works, one part per trade.
Clauses and documents to read
- IS 7272 (Part 1):1974 (labour output constants for building work, cited by number)
- CPWD Analysis of Rates (cited by name; use the current edition)
Cited by number and clause only. We do not reproduce clause text, tables or figures (BIS Act 2016, s.10(5) and s.11). Check the current edition and amendments before use.
References and further reading
Standard texts, listed in no order of merit. We do not copy text, figures, tables or solved problems from any book; our explanations and examples are original.
- B. N. Dutta, Estimating and Costing in Civil Engineering, UBS Publishers, latest edition.
Free and official sources
Found an error? Write to indiacongroupofengineers [at] gmail [dot] com. For corrections and feedback. We never ask for payment or personal details.