Earthwork is the first big activity on most civil sites. The right machine depends on the job: cutting, loading, hauling, spreading or compacting, and on the distance material has to move.

Bulldozers push material over short distances and rip hard ground. Excavators dig below their tracks and load trucks; backhoe loaders combine a small excavator and a front loader for light work. Wheel loaders lift loose material into trucks. Dumpers and tippers haul it. Motor graders shape fine levels and camber. Compactors finish the job: smooth-wheel rollers for granular and bituminous layers, padfoot rollers for cohesive soils, and vibratory rollers for deeper compaction.

Output depends on cycle time, bucket size, how full the bucket is, the swell of the material and how efficiently the machine is used in a working hour. Matching truck numbers to excavator output avoids both idle trucks and an idle excavator.

Safe earthmoving needs planned haul roads, banksmen for reversing machines, shoring or battering of deep cuts, and checks for buried services before digging.

Choosing between owning and hiring equipment is a cost decision. Owning makes sense when a machine will be busy for years; hiring suits short peaks. Either way, records of hours worked, idle time, fuel and breakdowns let the site team compare actual output with the plan.

Key formulas
  • Hourly output = (bucket volume × fill factor × efficiency × 3600) / cycle time in seconds
  • Number of trucks ≈ truck cycle time / loading time per truck
Solved example

Problem. An excavator with a 1.0 m³ bucket, fill factor 0.9, efficiency 0.8 and 25 s cycle. Find its output in loose m³/h.

  1. 1.0 × 0.9 × 0.8 × 3600 / 25 = 103.7 m³/h.

Answer. About 104 loose m³ per hour

Quick quiz

1Which machine shapes final levels and camber?

A motor grader.

2Which roller suits cohesive soil?

A padfoot (sheepsfoot) roller.

3Name one factor in excavator output.

Cycle time, bucket size, fill factor or efficiency.

References and further reading

Standard texts, listed in no order of merit. We do not copy text, figures, tables or solved problems from any book; our explanations and examples are original.

  • R. L. Peurifoy, C. J. Schexnayder, A. Shapira, Construction Planning, Equipment, and Methods, McGraw Hill, latest edition.
  • K. K. Chitkara, Construction Project Management, McGraw Hill Education (India), latest edition.

Free and official sources

All references for this subject →

Found an error? Write to indiacongroupofengineers [at] gmail [dot] com. For corrections and feedback. We never ask for payment or personal details.